Finlaggan Field

Block 21/5c

Operator: Zennor Pathway Limited
Partnership: Zennor Pathway Limited

Facts & Figures

AREA: 36.6 km2
SHARE: 100%
COUNTRY: UK
LICENCE EXPIRY May 2017
Summary

Licence P2013 was a 27th Round Traditional Licence award. The Block contains Finlaggan, a gas condensate accumulation originally drilled by ConocoPhilips in 2005. As Operator Zennor drilled an appraisal well (21/5c-7) and side-track (21/5c-7Z) with the Transocean Sedco 704 semi-submersible rig in Q2 2016. The side-track drill stem tested at a surface equipment constrained stable rate of 9,875 boepd (40 mmscfd of gas and 3,120 bbls/d of condensate).

In 2017 Zennor selected Britannia as the offtake route for the Finlaggan hydrocarbons and commenced detailed development planning.  The project FID decision followed in 2018, with the commencement of drilling operations in July 2018 and a formal Field Development Plan approval by the OGA on 18th October 2018.  Finlaggan will be developed as a 2-well subsea tieback to Britannia through a pipe-in-pipe subsea system controlled via an electrohydraulic umbilical.

First gas is scheduled for Q4 after the final tie-ins are completed during the tri-annual Britannia shutdown.

Click the links below to view our Environmental Statement Documents

Zennor Finlaggan Field Development ES (D-4201-2017)

Zennor Finlaggan_Public Notice_F01

Zennor Finlaggan_PON16 Form 24-08-17